Moving a part from prototype to production means freezing the design, running a DFM review before any steel is cut, and choosing the tooling that fits the volume. Many programs build an aluminum bridge mold first: it typically costs 30–50% less than a steel mold and ships parts in 3–5 weeks, while the steel production mold takes 6–10 weeks.


One housing, five ways to make it, priced by the builder's estimator. For this part the aluminum mold beats 3D printing at about 330 parts, and a multi-cavity steel mold beats re-cutting aluminum at about 32,000.
Parts per order
Lowest here: Aluminum bridge mold, $21.36 per part.
Urethane casting and CNC never win on price for this part. They earn their place on what they prove: a urethane part looks like production, and a machined part is real ABS. Your part's size, wall and resin move every crossover, so price your own part.
Seven steps from a frozen design to scheduled releases. Who owns each one is under its name.
You
Lock the revision you will tool. Anything still open goes on a list with an owner and a date; everything else stops changing.
Principal's tooling engineer, with your rep
Draft, wall, gates, parting line, ejection, undercuts and tolerances are checked against the process before mold design starts. Changes cost least here.
You sign off
The toolmaker sends the layout: parting line, gate and ejector locations, cooling and any slides. Approve it before steel is ordered.
Toolmaker
Typically 3–5 weeks for an aluminum mold and 6–10 weeks for P20 steel. Hardened, multi-cavity or slide-heavy tools take longer.
Principal
First shots are molded and measured. The process is tuned and steel is adjusted to size, usually in one or two loops.
Principal submits, you approve
Every drawing requirement is measured on production-process parts. Automotive and other regulated programs add a PPAP submission.
Principal and your rep
Pilot lots at production cycle time, then scheduled releases against your blanket PO while the rep watches delivery and quality.
A bridge mold does not make steel arrive sooner. It puts molded parts in your hands about six weeks earlier, from the process you will produce on.
Mold material sets shot life, lead time and how easily the tool takes a change. Budgetary figures are for the example housing.
| Aluminum | P20 steel | Hardened H13 | |
|---|---|---|---|
| Typical shot life | A few thousand to 10,000+ (unfilled resins) | 100,000–500,000 | 500,000 to 1,000,000+ |
| Build time | 3–5 weeks | 6–10 weeks | 10–16 weeks |
| Budgetary, this housing | About $10,000, 1 cavity | About $17,000, 1 cavity; $46,200, 4 cavities | Roughly 1.5× P20 |
| Cycle time | Often shorter: aluminum pulls heat out fast | Baseline | Baseline |
| Design changes | Easy to machine and weld-repair | Machinable; welds need care | Needs EDM, welding and re-hardening |
| Resins | Unfilled ABS, PC, PP, PE, TPE | Most resins, light glass fill | Glass-filled and abrasive resins |
| Best for | Bridge parts, launches under about 10,000, designs still moving | Most production programs | High volume and tight tolerance over millions of cycles |
The SPI mold classes put a number on life: Class 105 is a prototype mold for under 500 cycles, Class 104 runs up to 100,000, Class 103 up to 500,000, Class 102 up to 1 million and Class 101 beyond. Ask for the class on the quote so two toolmakers are pricing the same tool.
Glossary: bridge tooling, cavity, family mold, tooling ownership. Cost detail: injection mold cost guide.
Yes, for the right quantity and the right question. Neither proves the molding process; both put parts in hands without a mold.
| Urethane casting | 3D printing (MJF) | Aluminum mold | |
|---|---|---|---|
| Sweet spot | 10–200 parts | 1 to a few hundred | A few hundred to 10,000 |
| Tooling | Master pattern + silicone molds, about 20–25 parts each | None | Machined aluminum mold |
| Lead time | 1–3 weeks | 3–7 days | 3–5 weeks |
| Material | Urethanes that simulate ABS, PC, PP or rubber (30A–85D) | PA12 or PA11 nylon | Your production resin |
| Looks like production | Yes: color-matched, textured, painted | No: grainy grey or dyed black | Yes: molded surface and texture |
| Proves the molding process | No | No | Yes: gates, knit lines, shrink, sink |
| When it loses | Above a few hundred parts, or when the resin itself is being tested | Cosmetic parts, and tolerances tighter than ±0.012 in (±0.3 mm) | Under a few hundred parts, or when the design will change again |
Use cast or printed parts for marketing samples, fit checks and early field units. Use a bridge mold when the parts go to paying customers or into certification testing, because regulators and customers test the molded resin, not a look-alike. Compare: injection molding vs urethane casting, urethane casting vs 3D printing.
Freeze is the revision you tool. After it, the question is not whether a change is possible but whether it adds or removes steel.
| Change after tooling | Typical cost | Why |
|---|---|---|
| Add plastic: thicker wall, taller rib, bigger boss | Low | The toolmaker cuts steel away. This is a steel-safe change. |
| Remove plastic: thinner rib, smaller boss | High | Metal has to go back into the cavity by welding or a new insert, then be recut. |
| Move a hole or feature | Medium | Weld and recut, or replace an insert. |
| Add an undercut | High | Needs a slide or lifter, often a new plate and a longer cycle. |
| Change the resin | Medium to high | Shrink differs: ABS shrinks about 0.5%, polypropylene 1.5–2%, so critical sizes move. |
| Change the texture | Low to medium | A re-texture works only if draft allows: about 1.5° more per 0.001 in (0.025 mm) of texture depth. |
Design steel-safe where you expect to tune. Leave a critical dimension so the fix removes steel: a boss slightly small, a snap slightly shallow. The first T1 measurements then tell the toolmaker exactly how much to cut.
A DFM review before mold design is the cheapest change you will ever make. These are the checks principals run on a molded part.
Draft1–2° per side
Nominal wall0.060–0.120 in
Ribs and bosses50–60% of wall
Undercuts
Gate and knit lines
Parting line and ejection
Tolerances against capability±0.004–0.005 in
Full checklist: injection molding design review. The builder runs an instant DFM check on every estimate.

Tooling is done when parts from the production process measure to the drawing, and the process can keep them there.
T0 and T1. T0 shots prove the mold fills and ejects. T1 samples are measured against the drawing; the toolmaker adjusts steel and the process until they pass, usually in one or two loops.
First article. Every ballooned characteristic on the drawing is measured and recorded on parts made by the production process. See first article inspection.
PPAP, when required. Automotive and many industrial programs add a PPAP submission. Initial process studies usually need a Ppk of 1.67 or better on special characteristics; 1.33 Cpk is the common ongoing floor. See how quality works.
Bridge tooling is a lower-cost, faster mold or die, usually aluminum, that makes production-process parts while the long-life steel tool is built, or that covers a launch whose volume is still uncertain. It typically costs 30–50% less than steel and ships parts in 3–5 weeks.
Typically a few thousand to 10,000 or more shots in unfilled resins such as ABS, PC or PP, and fewer in glass-filled or abrasive resins. High-grade aluminum with good maintenance can run further. The toolmaker states the expected life on the quote.
When the design is stable, first-year volume is well above 10,000, the resin is glass-filled or abrasive, or the part needs multiple cavities from day one. A bridge mold only pays when you need parts sooner than steel can deliver or the design may still change.
For 10–200 parts that must look like production, yes: urethane resins simulate ABS, PC or rubber and take production colors and textures. Each silicone mold yields about 20–25 parts, so above a few hundred parts an aluminum mold is usually cheaper per part.
On most programs the buyer pays for the tooling and owns it, and the principal holds it on consignment. Ownership, maintenance and the right to move the tool belong in the purchase order. Customer-owned tooling can be moved to another molder with a compatible press.
Typically 12–16 weeks to approved production parts from a steel mold, including DFM, tool build, sampling and first article. With an aluminum bridge mold, first molded parts usually arrive in 5–6 weeks while the steel is built.
Processes on this page: injection molding, urethane casting, 3D printing, CNC machining.
Find where your part crosses over.
Build or upload the part for an instant budgetary estimate at every quantity, with a DFM check. A rep routes the RFQ to principals who build bridge and production tooling.